Street Repair For Summer 2024

Tentative road work to begin on 07/29/24 (depending on weather). More information to follow once construction begins. 

*If your home is in one of these areas, there maybe a time where you may need to have alternate parking. Please plan ahead.

Watch HERE for the most up-to-date information on this project. 

Photo 2024.jpg

 

Listing of the Roads to have repair work done:

  • Oregon Ave – From 2nd St. S to Jefferson Court

  • 8th St. – From Minnesota Ave. to Hall Ave

  • Mendenhall Ave. – From Hwy 75 to Andrews Ave

  • Beede Ave. – From Hwy 75 to 14th St. N

  • 15th St. – From Minnesota Ave. to Beede Ave

  • Chet Drive – From 15th St. N to 16th St.

  • Gewalt Drive – From Minnesota Ave to Gewalt Drive Cul De Sac

  • Park Ave - Entire

  • Central Ave – Entire

  • Oak St. – From Wilkin Ave. to North End Cul De Sac

  • Crescent Drive – Entire

  • Prentiss Court – Entire

  • Hemlock Court – Entire

  • Brott Court - Entire

  • Grace Ave Entire

  • Siemers Court – From Main St. to Tower Way

  • Tower Way – From Siemers Court to Grace Ave

  • Fairway Court - Entire

07/11/24: Tentative road work to begin on 07/29/24 (depending on weather). More information to follow once construction begins. 

*No special assessments will be charged to residents.

The funding will be from a General Obligation Bond. 